ICONS Completed more than 100 assignments in last nine years requiring man hours ranging between 500 to 25000 per assignment for clients in India and abroad with services like Extended Basic Engineering, Detailed Engineering, Feasibility studies, DPRs, Project Management services, Procurement services, HAZOP studies, As-built and technical studies.

Detail Engineering

Sulphonated Naphthalene Formaldehyde

Project:
Sulphonated Naphthalene Formaldehyde (SNF) Plant
Scope of Work:
To perform Extended Basic engineering, Detail Engineering (Process, Civil&Structural, Piping) Procurement Assistance and 3D Modelling.

Formaldehyde and Derivatives Complex

Project:
Formaldehyde and Derivatives Complex
Scope of Work:
To perform Extended Basic engineering, Detail Engineering (Process, Mechanical, Civil&Structural, Piping, Electrical), Procurement Assistance and 3D Modelling.

Food Grade Phosphoric Acid Plant (80TPD)

Project:
Food Grade Phosphoric Acid Plant (80TPD)
Scope of Work:
To perform Extended Basic engineering, Detail Engineering (Process, Mechanical, Civil&Structural, Piping, Electrical, Instrumentation) and 3DModelling for Alamine section, NPZ section & Defluorination section.

Ammonia plant (300 MTPD)

Project:
Ammonia plant (300 MTPD)
Scope of Work:
To perform Detail Engineering (Piping and Stress analysis) and 3DModelling for Process Gas Ammonia Compressor & Syn. Gas Compressor.

NaOCl Tank & Truck Loading Area

Project:
NaOCl Tank & Truck Loading Area
Scope of Work:
To perform Detail EngineeringPackage (Process, Mechanical, Civil, Piping, Electrical, Instrumentation) and 3DModelling for Storage area.

Recovery of Hexane from Niro Dryer

Project:
Recovery of Hexane from Niro Dryer
Scope of Work:
To perform Detail Engineering Package (Process, Mechanical, Civil&Structural, Piping, Electrical, Instrumentation) and 3DModelling for Polymerization in HDPE plant.

Butanol Waste Liquid Permanent Transportation

Project:
Butanol Waste Liquid Permanent Transportation
Scope of Work:
To perform Detail Engineering Package (Process, Piping, Electrical, Instrumentation) and 3DModelling for Butanol plant & Logistics bay.

Molten Ammonium Nitrate Storage (30MT)

Project:
MoltenAmmonium Nitrate Storage (30MT)
Scope of Work:
To perform Detail Engineering Package (Process, Mechanical, Civil&Structural, Piping, Electrical, Instrumentation) and 3DModelling for Ammonium Nitrate Storage tank system.

Perfumer Plant, Odisha

Project:
Perfumer Plant, Odisha
Scope of Work:
To perform Extended Basic engineering, Detail Engineering (Process, Mechanical, Civil&Structural, Piping, Electrical and Instrumentation) Procurement Assistance and 3D Modelling.

Alkali Scrubbing System (SAP-1&2)

Project:
Alkali Scrubbing System (SAP-1&2)
Scope of Work:
To perform Basic engineering, Detail Engineering (Process, Mechanical Civil&Structural, Piping, Instrumentation) Procurement Assistance and 3D Modelling. Vapour Ammonia line routed 750Meter from DAP-1 to SAP-1&2 on the existing pipe rack.

Stress Analysis

Formaldehyde and Derivatives Complex

Project:
Formaldehyde and Derivatives Complex
Scope of Work:
To perform piping stress analysis as part of Detail Engineering.
No. of systems = 41, No. of critical lines = 117

Technical Study for PHA recommendation in PDH Plant

Project:
Technical Study for PHA recommendation in PDH Plant
Scope of Work:
To check adequacy of pipe supports for the interconnecting gas piping (two-phase flow, expected) between Deethanizer condenser (Kettle exchanger 2-E-3002) and Propylene compressor 1st stage suction drum (2-V-5001).
No. of elements =33


To check adequacy of pipe supports for handling expected two-phase flow in gas line (48”-PR-250082-A2A-V) with operating temperature of 45 ⁰C from Propylene compressor discharge in which propylene liquid is injected through line (10”-PR-250080-A2A-V) to cool it to 32 ⁰C.
No. of elements =201

Failure study of PG tapping and Support spring hangers for radiant coil pipes in EC Furnace

Project:
Failure study of PG tapping and Support spring hangers for radiant coil pipes in EC Furnace
Scope of Work:
To check the failure of ¾” PG tapping connections on the 2”pig tails (radiant coils) and check the radiant coilsupport hangers are not moved back to the set positions during cold conditionsof Ethylene Cracking furnacefeed inlet header and outlet header for all seven furnaces.
No. of elements =2177

Bellow Failure study in 48” GRP Flue gas line in EC Plant

Project:
Bellow Failure study in 48” GRP Flue gas line in EC Plant
Scope of Work:
To check the failure of expansion bellow and minimize the vibrations in GRP piping discharge flue gas duct line 48”-QG-335524-GRPN from Separation vessel (3PK-3501-TK2) to Caustic scrubber (3PK-3501-C1).
No. of elements =45

SAAC LP Steam Header (20”) in Acrylic Acid plant

Project:
SAAC LP Steam Header (20”) in Acrylic Acid plant
Scope of Work:
To checkadequacy of existing supports for 20”LP steam headers (Eastand West) of Air-cooled heat exchangers(18Nos).
No. of elements =334